Hat Head Sewer Treatment Plant

Cost: $146K

Contractor: Coastal Works

Client: Kempsey Shire Council

Client Referee: Wesley Trotter, Kempsey Shire Council Process Engineer

Works at Hat Head STP, for Kempsey Shire Council included installation of two new inlet works return pumps, all associated pipe work, additional access platforms and fall arrest davit points.

The work needed to be planned around keeping the plant operational at all times and completing the pump installation before Christmas Holiday period peak flows.

The Coastal Works Mechanical and Electrical team delivered all works to provide a turnkey solution on time and under budget.